Schedule for the Xfce 4.8 Development Cycle

Dates Phase/Deadline Everyone's Tasks Release Team Tasks Maintainer Tasks
2009-08-16 - 2009-08-30 Planning Phase Elect the release team, discuss dependencies Make a realistic list of planned features
2009-08-31 - 2010-01-31 Development Phase Support Xfce Supervise development, remind people of deadlines Hacking
2009-08-31 - 2009-09-13 Extended Planning Phase May request dependency changes
2009-09-13 Dependency Freeze Update dependency info, inform community about the decisions made (dependencies, unguaranteed feature preview)
2010-02-01 - 2010-04-12 Release Phase Wait patiently Perform releases, remind people of deadlines Perform releases of own components if desired
2010-02-01 Xfce X.Ypre1 (Feature Freeze) Prepare release announcements 2 days before, release Xfce X.Ypre1 Make sure the latest development release is in good shape and uploaded
2010-03-01 Xfce X.Ypre2 (String Freeze) Prepare release announcements, release Xfce X.Ypre2 Make sure that strings in the latest development release or in master are good
2010-03-29 Xfce X.Ypre3 (Code Freeze) Prepare release announcements, release Xfce X.Ypre3, create ELS branches Make sure the latest development release is in good shape, or that code is solid/finished in master
2010-04-12 Xfce X.Y (Final Release) Celebrate Prepare release announcements, release Xfce X.Y, branch for stable release, merge ELS branches into master Make sure to upload a new release of own components before this deadline